Two wet scrubbers installed and commissioned within a tight mine-wide shutdown window.

49.73332, -114.88532

Teck Coal Line Creek Operations Dust Collection System — Sparwood, BC

Teck Coal had a tight maintenance shutdown window and needed a new scrubber facility built to fit it. Wildstone delivered. Working under an accelerated schedule aligned with mine-wide operations, Wildstone constructed two structural steel buildings and completed all mechanical and electrical work to install and commission two new wet scrubbers.

The 1,800 sq ft scrubber building was built with concrete foundations, structural steel framing, insulated metal composite cladding, and a standing seam metal roof built for an active industrial environment. Wildstone self-performed the full mechanical scope in-house, with tight coordination around mine operations and shutdown sequencing from start to finish.

Sparwood, BC

Coordinates

49.73332, -114.88532

Project

Teck Coal Line Creek Operations Dust Collection System

Status

CompletedSpring 2013

Let’s Get to Work