Robert Service School Mechanical Upgrades
A full heating system replacement — scheduled around 500 students and never missing a bell.

Robert Service School Mechanical Upgrades
Replacing a heating system in a fully operational K-12 school takes more than mechanical expertise. Wildstone completed the $5.8M full removal of Robert Service School's aging oil-fired boiler system and installed new high-efficiency propane-fired boilers, a dual-boiler propane plant, upgraded air separator, and new circulation pumps.
Re-piping, hydronic modifications, and all electrical and control upgrades were scheduled outside school hours or around planned shutdowns, keeping disruption to a minimum for students, staff, and a full academic calendar. The result is a cleaner, more efficient heating system for one of Dawson City's most essential community buildings. Delivered for the Government of Yukon.
Coordinates
64.0639, -139.4333
Project
Robert Service School Mechanical Upgrades
Status
Completed — Fall 2024