Cache Creek Water Treatment Plant
A water treatment plant expansion built in a public park, including four greensand filters, precision tank lifts, and continuous dewatering in a high water table environment.

Cache Creek Water Treatment Plant
Wildstone expanded the Village of Cache Creek's water treatment capacity by installing four manganese greensand filters, new chemical injection lines, hypochlorite storage, and all associated process mechanical tied into the existing water system. A pre-engineered building was constructed atop several holding and backwash tanks, with new site piping and tie-ins installed within the local park. The project required continuous dewatering throughout construction due to a very high water table, and precision crane work for tank placement and lifting. The constrained, high-traffic park setting added complexity to site logistics and sequencing.
Coordinates
50.8167, -121.3333
Project
Cache Creek Water Treatment Plant
Status
Completed— Spring 2013
Photo Gallery